Enrolment Wave: SIT, QT
|
Enrolment involves an LDC’s formal testing with the MDM/R: | |
| • | System Integration Testing (SIT) ensures that all system information exchanges required for the meter to bill process can be fulfilled through testing of MDM/R interfaces (10 business days). |
| • | Qualification Testing (QT) occurs when SIT is completed and focuses on the impact on business processes. QT mimics four billing cycles but compresses them into a shortened time frame (21 consecutive days). |
| • |
An LDC should also prepare for cutover to the MDM/R production system as it progresses through QT. |
| Registration Forms Role: LDC Project Lead |
|
|
Smart Metering Entity SME-LDC Agreement LDC cutover strategy | |
| Testing Role: LDC & SME |
|
|
SIT and QT testing | |
|
Training |
|
| Business Process Dev't Role: LDC Project Team |
|
|
Test new and modified business processes before MDM/R production and make final adjustments. Develop missing processes that might be identified through testing. | |
| Reporting Role: LDC Project Lead |
|
|
Participate in daily conference calls with SME test teams Communicate progress internally
| |
| Communications Role: SME Project Lead |
|
|
Conduct daily conference calls with LDC test teams and coordinate technical assistance. | |
| Documents Role: SME |
|
|
LDC cutover strategy | |