Enrolment Wave: SIT, QT

 

Enrolment involves an LDC’s formal testing with the MDM/R:

•  System Integration Testing (SIT) ensures that all system information exchanges required for the meter to bill process can be fulfilled through testing of MDM/R interfaces (10 business days).
•  Qualification Testing (QT) occurs when SIT is completed and focuses on the impact on business processes. QT mimics four billing cycles but compresses them into a shortened time frame (21 consecutive days).
• 

An LDC should also prepare for cutover to the MDM/R production system as it progresses through QT.

 
Registration Forms
Role: LDC Project Lead
 

Smart Metering Entity SME-LDC Agreement

LDC cutover strategy

 
Testing
Role: LDC & SME
 

SIT and QT testing

 

Training
Role: LDC & Agents

 
 
Business Process Dev't
Role: LDC Project Team
 

Test new and modified business processes before MDM/R production and make final adjustments.

Develop missing processes that might be identified through testing.

 
Reporting
Role: LDC Project Lead
 

Participate in daily conference calls with SME test teams

Communicate progress internally

 
Communications
Role: SME Project Lead
 

Conduct daily conference calls with LDC test teams and coordinate technical assistance.

 
Documents
Role: SME
 

LDC cutover strategy

  • MDM/R Baseline SIT Scripts R7.0
  • MDM/R Baseline QT Scripts R7.0
  • MDM/R Baseline SIT Scripts R7.2
  • MDM/R Baseline QT Scripts R7.2



  •