Testing Readiness
During this period, LDCs ensure their systems are ready for testing. They also arrange Applicability Statement 2 (AS2) connectivity testing with the MDM/R through the Smart Metering Entity (SME). |
| Infrastructure Role: LDC | |
Complete system installations and upgrades | |
| Registration Forms Role: LDC Project Lead | |
Provide LDC digital certificates to SME Links to forms required are at the bottom of this page | |
| Testing Role: LDC & SME | |
LDC AS2 and firewall configuration and internal testing Schedule MDM/R connectivity tests | |
Training | |
MDM/R Graphical User Interface Training: Please contact us to arrange. | |
Business Process Dev't Role: LDC Project Team | |
Continue with business process development and reengineering | |
| Reporting Role: LDC Project Lead | |
Periodic SME status updates Communicate progress internally
| |
| Communications Role: SME Project Lead | |
The SME will confirm wave assignment based on a review of the LDC’s project plan. | |
| Documents | |