Testing Readiness

 

During this period, LDCs ensure their systems are ready for testing. They also arrange Applicability Statement 2 (AS2) connectivity testing with the MDM/R through the Smart Metering Entity (SME).

Infrastructure
Role: LDC

Complete system installations and upgrades

Registration Forms
Role: LDC Project Lead

Provide LDC digital certificates to SME

Links to forms required are at the bottom of this page

Testing
Role: LDC & SME

LDC AS2 and firewall configuration and internal testing

Schedule MDM/R connectivity tests

Training
Role: LDC & Agents

MDM/R Graphical User Interface Training: Please contact us to arrange.

Online simulations

Business Process Dev't

Role: LDC Project Team

Continue with business process development and reengineering

Reporting
Role: LDC Project Lead

Periodic SME status updates

Communicate progress internally

Communications
Role: SME Project Lead

The SME will confirm wave assignment based on a review of the LDC’s project plan.